|
EVALUATION
METHODOLOGY:
PROJECT
IMPLEMENTATION RISK ASSESSMENT
Merlin
commonly evaluates projects
utilizing a risk assessment
criteria. Merlin assesses the
likely outcome due to various
failure scenarios of the project
execution plan.
The
Operator and Prime Contractor
usually place emphasis on achieving
on-time and under-cost completion
and do not always provide contingency
planning until a crisis develops.
The project execution plan as
agreed between Operator and
Prime Contractor is usually
realistic for the specified
assumptions but is probably
neither optimistic nor overly
pessimistic. It is most often
described as a plan with a 50%
probability of being achieved
within budget and schedule
it also has a 50% probability
of exceeding the cost estimate
and not being completed on time
if it has truly been developed
with this philosophy.
In
addition to cost and schedule
variance, the other major project
risk exposure is confidence
in reliability and capacity
of the project facility. Merlin
has a unique history and reputation
for providing both technical
risk analysis and standard project
risk analysis. Technical risk
analysis includes detailed review
of the process technology, the
specific hardware to be used,
and the overall project implementation
planning.
Merlin Associates
will provide a set of risk criteria
or a band of predicted outcomes.
The basis of Merlins risk
analysis is development of an
independent capital cost estimate
using Merlins proprietary
Capital Cost Estimators. Merlins
proprietary project schedule
is linked to the capital cost
estimator. Merlin has developed
and maintained a summary level
project schedule for each of
the LNG chain segments utilizing
only sufficient activities to
determine project duration,
critical path activities, and
sufficient activities to allow
detailed capital cost estimating.
The summary level project schedule
will typically have 400 - 600
activities depending on whether
the full feedgas system is included
or not. The Merlin summary level
project schedule with the Merlin
capital cost estimate predicts
expenditure phasing on monthly
and annual time periods.
The capital
cost estimate with the associated
project schedule is the Merlin
deterministic capital cost estimate.
This detailed estimate is summarized
to 30 - 50 major cost categories
for probability analysis. Statistical
probability analysis for the
costs and schedule is done using
the @Risk program with Latin
Hypercube random sampling of
all the assigned probability
distributions. We use triangular
probability distributions and
take into account the affects
of cost/schedule variables that
have internal dependencies with
other cost/schedule variables.
A typical probability analysis
requires from 750 - 1500 iterations
in order to produce smooth probability
curves.
Although
the full spectrum of project
probabilities are developed,
Merlin typically report the
Mean non-exceedance probability
data (usually similar to the
projects 50% probability
data); the 75% non-exceedance
probability data (sometimes
called "Most Likely");
and the 95% non-exceedance probability
data (often called the "Worst
Case Scenario"). The Merlin
75% probability data is a prediction
of project outcomes assuming
industry average problems, engineering
judgment of additional project
costs for the site-specific
location to resolve these problems,
and adjustment for known site-specific
problems. The 95% probability
data assumes a higher frequency
and duration of problem occurrences.
The
complete risk analysis method
is justified for the financing
community on all LNG grass roots
chain projects and most expansion
projects. It is frequently justified
for many of the equity participants
who often do not have internal
technical expertise in LNG technology
and an up-to-date database of
LNG project costs. Use of a
third party consultant jointly
by the LNG sellers and buyers
is useful to eliminate internal
disagreements and can greatly
assist in reaching agreement
on the actual details of the
final sales agreement. Most
LNG projects are multi-participant
projects where an independent
third party used jointly by
all parties can be very helpful
in avoiding internal conflicts.
|