|
UNIQUE
QUALIFICATIONS
LNG chain projects involve feedgas,
pipelines, liquefaction, shipping,
regasification, and end-user
facilities and are typically
extremely capital intensive
(US$ 2 - 15 billion).
LNG
chain projects require a very
long period of capital expenditure
during the design, procurement,
and construction phases (3 -
5 years) before there is any
income, and, due to their large
size and complexity, are nearly
always multi-participant projects.
It has become very common to
use project financing for these
projects since their large required
investment exceeds the available
internal financing of all but
the very largest international
energy companies. Securities
issues are also available as
an alternative financing facility
for many LNG projects.
Most large
energy projects have a loan
collateral basis that can be
evaluated the recoverable
hydrocarbon reserves that will
be produced by the project.
Due to the very large investment
and the large volume of energy
reserves that will be processed
by the typical LNG project,
the projects recoverable
hydrocarbon reserve collateral
cannot be considered liquid
in the normal sense. This leads
to a project without a prime
source of loan collateral for
project financing.
The only source
of collateral to the investing
or financing participant is
the firm long term LNG or power
sales contract between sellers
and buyers although the sales
contract must be to buyers that
are regarded as very financially
sound companies. This type of
exposure for both the equity
participants and the international
financing community traditionally
requires conservative project
evaluation and risk analysis.
A LNG chain
project that is not complete
(including all the segments)
and capable of meeting its sales
contract requirements has essentially
no value as an asset against
the loan. The salvage value
of even the best available gas
processing/shipping/regasification
technology is very low without
something to process. The only
loan value is essentially the
sales revenue generated after
the chain begins operation.
Although historically
this has always been a problem
for LNG projects, the problem
has become critical since about
1980 for several reasons.
- The
size (and cost) of a world
class base load LNG plant
has dramatically increased
since the industry began in
the late 1960s. This
is largely a result of utilizing
economies of scale through
ever larger facilities in
order to obtain minimum unit
costs.
- The LNG
facility is built of high
cost critical new technology
components that have tended
to have the highest inflation
rates although overall inflation
rates have been very low since
1988.
- The facilities
are constructed using mostly
the highest skill level construction
workers that are in short
supply the world over, their
wage rates have tended to
increase with the greatest
rate of acceleration.
- The onstream
time for all the facilities
in the chain is critical to
project economic return. All
the chain components tend
to be extremely conservative
in providing redundant backup
equipment and this philosophy
became extreme during the
1980s.
- Newest
proven technology and increased
automation have been steadily
implemented in LNG projects
to reduce operating and maintenance
costs as well as to improve
onstream operating factors.
This has tended to increase
initial capital investment.
For all these
reasons, the LNG project participants
have increasingly used outside
third party technical consultants
to evaluate project costs, technical
risks, project schedule, and
efficiency of design. Merlin
Associates was in fact started
to fulfill this demand. Merlin
has been the technical consultant
to the financing community on
nearly all LNG base load grassroots
installations and LNG expansions
built since 1983. We have also
provided similar services to
several of the equity participants
on the same projects during
this same period. Merlin has
also provided consulting services
for preliminary feasibility
studies for many operating companies
considering entry into the LNG
business and to several LNG
buyers during this period.
Merlin is
in the unique position of having
a very detailed and inclusive
LNG capital cost database as
a result of providing consulting
services to nearly all the existing
LNG projects in the areas of
efficiency improvement and debottlenecking
combined with our work in support
of LNG project financing. Most
companies who would have this
information are either the major
energy companies operating the
facilities or the very large
engineering companies who have
provided the detailed engineering
for the LNG projects. Neither
of these parties is an easy
source of cost data. The operating
companies must protect their
competitive positions and will
not willingly share expensive
information. The engineering
companies will provide the services
but at a very high price
their equivalently experienced
personnel are most efficiently
used in directing and managing
detailed design of very large
projects, not providing consulting
services where the major charge
is only for their own time.
Merlin has
detailed cost breakdowns for
nearly all the LNG projects
installed. We do not provide
the actual data from our database
but do use it to provide our
consulting services to our clients.
We carefully and rigorously
protect our clients confidential
information but are able to
provide a valuable service in
a timely manner due to being
a small and specialized consulting
engineering company. We pride
ourselves on being very efficient
through the use of leading edge
computer technology and have
the most current process engineering,
CAD, mathematical and statistical
analysis software programs,
and a very large library of
standard business software packages.
Merlin Associates
have equivalent experience and
expertise in the areas of offshore
and onshore oil and gas production
facilities, pipelines, and natural
gas processing.
Merlin have
used imaginative and innovative
methods of adapting standard
software packages to quickly
provide capital cost estimating
that is fully backed up and
supported down to actual bills
of material for our highest
quality cost estimates.
Merlin has
been a leader in developing
a consistent methodology for
project technical, capital,
and schedule risk analysis for
LNG projects. This developing
methodology has been utilized
to develop our proprietary cost
estimating models.
|