HOME | WORK WITH US | UNIQUE QUALIFICATIONS | ABOUT US | OUR CLIENTS | CONTACT US

MERLIN ASSOCIATES

EVALUATION CRITERIA and
SPECIFIC RISK ANALYSIS EXECUTION

When performing Independent Engineer services for project financing Merlin Associates performs risk analysis of all the major project implementation activities.

These normally include the following areas of risk analysis:

TECHNICAL DESIGN ANALYSIS

  • Process System All Project Facilities – Feedgas production, field processing, gas conditioning, and liquefaction plus supporting utility systems, shipping distances and available shipping capacity, import regasification and power generation facilities with review of local marine facilities.
  • Process Technology utilized in the process and utility systems in all project facilities.
  • Foundation and Support Structure Design For Offshore Feedgas Facilities
  • Pipeline Feedgas Transfer Systems
  • Review of LNG Storage, Loading/Unloading, and Shipping Systems
  • Review of Power Generation systems
  • Review of Delivery Point Requirements
  • Merlin can simulate the total project operation to evaluate how much excess capacity there is available in each link of the LNG Trade chain. This will provide an indication of potential future expansion capabilities as well as determining how much potential there is to make up delivery shortfalls.

return to top>>

PROJECT MANAGEMENT and SYSTEMS

  • Project management system and major project participant organizations to be used relative to the project execution plan.
  • Key personnel and their experience on similar projects in similar locations.
  • Proposed project staffing levels by operator, project manager, and installation contractor.
  • Proposed short-list of major contractors and sub-contractors if available.
  • Project management definitions, procedures, and systems to be used for progress reporting, cost commitment and expenditure reporting, updating project cost estimates, change orders, and variance trend analysis.

return to top>>

PROJECT SCHEDULE

  • Permitting status and requirements.
  • Current status of the basis of design, design engineering schedule and relationship with procurement and construction.
  • Major contractual philosophy, procurement methods, proposed sourcing, procurement scheduling and relationship with engineering, fabrication, and construction.
  • Fabrication location(s), experience history, resource availability, technical competence of supervision and workforce, transportation scheduling.
  • Transportation and offshore installation, construction, and support vessel capabilities and availability, and availability of alternate vessels for the offshore feedgas facility installation.
  • Installation, hookup, and commissioning scheduling for the offshore feedgas system.
  • Construction location, potential infrastructure requirements during construction and operations.
  • Availability of engineering, construction, and supervision labor resources, major contractor work history, and review of actual contractual agreements.
  • Start-up scheduling.
  • Overall available flexibility and consequences of slippage.

return to top>>

PROJECT IMPLEMENTATION

  • Review of the Project Development Plan for the overall project and for each of the LNG Chain Segments for the project.
  • Review of past performance and experience level of each of the major participants in each segment of the LNG Chain Project. Includes both Sponsor side and Contractor/Vendor/Manufacturer side.

return to top>>

ESTIMATED CAPITAL COSTS
The actual potential variance for a project developed 50% probability non-exceedance capital cost budget estimate is primarily a function of the type of contractual agreement used to supply the facility. A lump-sum turnkey contract may have almost zero cost overrun potential, although a significant schedule slippage will usually expose the Operator to additional non-recoverable costs. A typical reimbursable fixed fee contract will usually have from 10 to 25% potential cost overrun variance with 5 to 10% cost underrun potential.

Merlin’s Capital/Operating Cost Estimating Models produce a high accuracy cost estimate assuming that similar technology and facility throughputs are specified for the new project. The models develop their estimates using actual performance data from existing projects. The model cannot reflect new technology, significant shifts in competitive bidding, or non-traditional implementation planning. The estimate produced provides a high accuracy cost estimate that provides a yardstick against which all significant variances are rigorously analyzed. On the basis of this analysis the variances are either confirmed or projected as suspect.

The Merlin cost estimate also reflects the previous analysis of technical design, project management, and predicted implementation planning and schedule. Adjustments are often reflected for additional schedule flexibility, the state of definition of the project basis of design, historical performance of the Operator and proposed major Fabricators and Contractors, as well as previous experience at similar project locations by other projects.

return to top>>

OPERATING and MAINTENANCE COSTS
Merlin Associates reviews project operator’s or technical manager’s proposed staffing methods and levels, proposed maintenance programs, and predicted maintenance costs.

Merlin Associates’ Capital Cost Estimators include a database of operating costs for various type facilities of many different companies to predict average annual operating costs for proposed new projects. The estimate basis is operation at design throughput conditions. The estimate is based upon historical information from other facilities with the same type of equipment. The estimate is sensitive to basic wage rates, staffing levels, design throughput, environmental operating conditions, age of the facility, how heavily loaded the facility is in relation to its design capacity, and a weighting for technical operating competence and maintenance quality.

return to top>>

UNIQUE ASPECTS of the IMPORT TERMINAL CAPITAL COST ESTIMATING MODEL
Capital cost data for specific LNG import terminals included in the Merlin LNG Import Terminal Capital Cost Estimating Model database have been updated to reflect current costs for LNG storage tanks, unloading systems, relief and blowdown systems, and utility systems derived from LNG liquefaction plant projects using similar/identical equipment and from the few actual LNG Import terminal projects which have been implemented in the recent past.

LNG import terminals, because of their location and dependency on gas sendout demand pattern are even more site and project specific than liquefaction plants. The Merlin LNG Import Terminal Capital Cost Estimating Model is based on a design philosophy typical for a major international energy company being installed in Europe or the US and in emerging energy markets of developing countries, typically supplying a large electric power generation plant. It does not reflect the highly conservative basis of design used for Japanese import terminals with their unique safety, security of supply, environmental, and demand characteristics.

Estimating methodology is similar to that used in the liquefaction model. A project specific equipment list is developed using appropriate capacity and escalation factors. Bulk material costs are calculated from factors against related equipment costs based on actual installation cost data. Labor manhours are developed on a US Gulf of Mexico basis and labor costs calculated based on expected site productivities relative to the US Gulf of Mexico and site specific "all-in" labor rates.

The model results have been demonstrated to be within ± 10% of lump-sum cost estimates prepared by engineering-procurement-construction contractors using the same basis of design characteristics.

return to top>>

EVALUATATION METHODOLOGY

EVALUATION CRITERIA and SPECIFIC RISK ANALYSIS EXECUTION

PROJECT EXPERIENCE

RESUMES of KEY PERSONNEL


© COPYRIGHT 2001 MERLIN ASSOCIATES